Route survey
Our survey team set out the tower locations along the route with a total station, and checked them again before each foundation was started.
Progress from every MRCC site currently in hand, posted as the work moves forward, with photographs from the field.
Our survey team set out the tower locations along the route with a total station, and checked them again before each foundation was started.
The crane, piling rig, water bowser and foundation equipment were brought to site, and the site yard was set up for the bored pile foundations.
The piling rig bored the foundation piles at each tower location. The reinforcement cages were lowered by crane, the casings and stubs were set to line and level, and the piles were concreted.
Foundation work on the section was completed in April 2026.